New Science Building Painting & Classroom Design
Work on Massasoit's new Science Building has progressed with work on the exterior and interior adding... ...
Massasoit’s Transformation Through Renovation Project is a $52 million capital project that will bring state-of-the-art classrooms and labs to the College’s Brockton campus. The multi-year project, which began in July 2022, includes the gut-rehab of two instructional buildings to create a new Science building and a new Health Sciences building. The new spaces – designed with input from students, faculty, and staff – will impact thousands of students across nearly all of Massasoit’s academic divisions, and will enhance how the College trains our community’s future professionals.
Work on Massasoit's new Science Building has progressed with work on the exterior and interior adding... ...
Steering Committee – Policy & Decision Making
President Bill Mitchell; Vice President Margaret Gazzara Hess; Vice President Bill O'Neill; Interim Vice President Rita Jones-Hyde
To define in detail space requirements to meet current & future programmatic needs.
David Auperin; Michael Bankson; Susan Clover; Kevin Doten; Ana Estabrooks; Rachel
Franciosi; Richard Hadley; William Hanna; Eve Jankey; David Johanson; Denise Logan;
Marie McDonnell; Melany McFadden; Bill O’Neill; Catherine Powers-Ozyurt; Andrew Oguma;
Jennifer Pike; Katie Ruggieri; Jesse Schreier; Amee Synnott; Andrea Torres; Kendra
Twomey
To identify and recommend swing space and the construction process.
Angelina Avedano; Paul Chiano; Richard Hadley; Jen Holbrook; Rita Jones-Hyde; Jeffrey
Mei; Michael Mezzano; Bill Morrison; Bill O'Neill; Kim Sylvia; Christofer Volz
To provide project teams with technical expertise related to Information Technology.
Jackie Barrett; Patrick Mauretti; Bill Morrison
To provide periodic updates to the college community on the status of the project.
Jen Holbrook; Amity Kelley; Lloyd King; Bill Morrison; Alex Villanueva; Karina Sallaway
To build a capital campaign to support the philanthropic source of funding.
President Mitchell; Margaret Downey; Alex Villanueva
| Project Tasks | Dates | Approximate Months |
|---|---|---|
| Project Prep/Scope Confirmation | July 2022 - August 2022 | 2 - Completed |
| Select Architectural Firm (DSB) | September 2022 - November 2022 | 3 - Completed |
| Study, Schematic Design | December 2022 - December 2023 | 12 - Completed |
| DCAMM Certification of Study | December 2023 | 1 - Completed |
| Detailed Design/Construction Documents | January 2024 - March 2025 | 15 - Completed |
| Bidding/Permitting | March 2025 - May 2025 | 3 - Completed |
| Construction - Liberal Arts to New Science Renovation | May 2025 - July 2026 | 15 - In Process |
| Construction - Science to New Nursing & Allied Health | July 2026 - July 2027 | 12 |
| Approx. Total Months | 63 |
April 13, 2022 - Massasoit Community College announced as a recipient by Governor Baker in the latest round of Higher Education Capital Grants.
June 28, 2022 - President DiPasquale charges Project Teams that will work collaboratively with faculty and staff on key capacities.
August 3, 2022 - Designer Selection Board chooses Jones Architecture for architectural & engineering services.
October 25, 2022 - Start-Up Workshop held with DCAMM, Jones Architecture/Studio Luz, Design Consultants, Massasoit Project Teams
November 7, 2022 - Project Planning Meetings (Review of 2019 Readiness Report and Inclusive Design)
November 14, 2022 - Science, Math, Nursing, and Allied Health Programming Meetings and Building Walkthroughs (#1)
December 7 & 9, 2022 - Science, Math, Nursing, and Allied Health Programming Meetings (#2)
January 17 & 18, 2023 - Faculty and Staff Local College Site Visits for Recently Renovated Science, Nursing, & Allied Health Spaces
January 24, 2023 - Science, Math, Nursing, and Allied Health Programming Meetings (#3)
March 8 & 9, 2023 - Campus Community Engagement Session #1 & Project Update for Massasoit Project Teams presented by DCAMM, Jones Architecture/Studio Luz, Design Consultants
March 30, 2023 - Respiratory, Science & Math Programming Meeting (#4)
April 18 & 27, 2023 - Nursing Programming Meetings (#4)
June 14, 2023 - Existing Furniture & Systems Walkthrough with Design Team, DCAMM, BVH, Science, Nursing, and Allied Health Faculty and Staff
August 21, 2023 - Schematic Design Kickoff Meeting with all Project Teams (Dining Hall)
October 16, 2023 - Universal Design Workshop #1 (SD)
November 3, 2023 - Universal Design Workshop #2 & Interior Experience Meeting #1 (SD)
November 14, 2023 - Campus Community Engagement Session #2 for Massasoit Project Teams and Campus Community presented by DCAMM, Jones Architecture/Studio Luz, Design Consultants
December 15. 2023 - Interior Experience Committee Meeting #2 (SD)
August 6, 2024 - *Building Experience Committee Meeting #1 (DD)
*(newly combined Committee from Interior Experience & Universal Design)
August 6, 2024 - Science, Nursing, Allied Health Meeting (DD)
September 16, 2024 - Building Experience Committee Meeting #2 (DD)
October 18, 2024 - Building Experience Committee Meeting #3 (DD)
November 2, 2024 - Open House Poster Display
December 5, 2024 - Student Senate Engagement Workshop
July 16, 2025 - Science Building Groundbreaking
(SD) = Schematic Design Phase
(DD) = Detail Design Phase