Work on the new Science Building has progressed with work on the exterior and interior adding color, installation of the greenhouse glass, classroom furniture, solar tubes in rooms without windows, and other light fixtures.

Next on the schedule is tile work in the bathrooms and greenhouse, plumbing fixtures in classrooms and bathrooms, ceiling tile installation, and corridor millwork.

Exterior painting work on the new Science Building.

Exterior work continues on the new Science Building.

New classrooms ceiling and paint set-up in the new Science Building.

Updated ceiling tiles, wiring, and painting in the new classroom set-ups in the new Science Building.

Solar tube in a classroom in the new Science Building.

Solar tubes have been installed in some classrooms and offices in the new Science Building.

Lab equipment and storage inside new Science Building.

Lab equipment and storage are starting to be installed in classrooms lab spaces inside the new Science Building.

Shades of orange paintwork on walls in the new Science Building.

Shades of orange paintwork is being used to differentiate classroom, lab, and student spaces in the new Science Building.

Greenhouse framing and glass work.

The greenhouse is looking more complete with the framing and window work.