Work continues on the new Science Building with wiring, including initial fire alarms, installation of panels, main switch board, and transformers, and additional work on the exterior soffits.

Drywall can be seen throughout the interior, giving a better visual of how hallways, classrooms, and offices will look. The most noticeable work done since the last update is the framing of the greenhouse, which can be seen above.

Next on the schedule is further work on the greenhouse, glazing and mudroom installation, and the installation of lab rooms flooring, light fixtures, and sprinkler drops.

Interior wire work in the new Science Building.

Interior wire work continues in the new Science Building.

Soffit installed on the exterior ceiling of the new Science Building

Soffit was installed on the exterior ceiling of the building, providing a new visual for how the finished building will look on the outside.

Drywall installed in a hallway of the new Science Building

Drywall was installed on the interior walls of the building, providing a new visual for how the finished building will look.

Drywall work inside new Science Building.

Work is ongoing to the interior of the building, giving shape to classrooms, labs, and other spaces now that drywall has been installed.

Greenhouse under construction at Massasoit

The new future greenhouse attached to Massasoit's new Science Building.

Greenhouse framing work.

Greenhouse framing work before glazing and mudroom installation.